Project Info
- Construction Date: 2004 to 2018
- Category: Overhaul Supervision & Project Management
-
2018 :
AllGen staff provided technical support for the Unit 5 Mitsubishi-Hitachi power system HP, LP and Generator rebuild and Unit 4 Generator rebuild included full strip down Hydrogen Dryer and reassembly of the exciter.
AllGen’s sister company proGen provided project management staff for five Unit overhauls at Huntly Power tation during the period 2004 until 2012... 800 tons per hour CE boilers driving 250 MW Parsons Turbines and Generators.
Project management responsibilities included safety management, risk management, budget management and contractor management. In addition, the project manager was responsible for coordinating and managing the local power station staff involved in the supervision, technical engineering and hands-on maintenance of the overhaul.
In addition during all overhauls ProGen staff developed and provided on-going monitoring and status reporting for the overhaul plan. Typically there were 4000 tasks involving a multitude of client trade and contractor resources.
During the overhauls from 2005 to 2007, ProGen also provided management support with the addition of a coordinator to organise the NDT testing and the overhaul related purchasing during the overhauls.
All overhauls were completed successfully.
Project Details
AllGen & Genesis staff removing 250 MW Generator rotor